Deming Park Pathway is a state certified project that we started in April as a subcontractor for Wabash Valley Asphalt. The asphalt trail will start in Deming Park and end after Lincoln .
The project consists of excavating the trail, building modular block walls, and ADA ramps. The project is estimated to be complete in October 31, 2010.
Maple Ridge Apartments is a retirement community funded by federal stimulas money located in Paris Illinois. We will be a subcontractor to Core Construction and B & T Excavation.
The project consists of total site construction such as utilities, drainage, roads, sidewalks and curbs and should be completed at the end of 2010.
Burford Dock
Remove and replace loading dock area with new concrete.
Wall at 5th & Chestnut
Remove corner wall and replace with curb.